Paving Project Begins
On May 23rd the Lancaster County Engineering Department sent letters to landowners, to inform them of the upcoming road pavement project for SW 42nd Street.
In this letter, it was announced that construction would begin on June 6th and be complete by end of July, weather permitting.
A couple things to note:
Prior to the start of the project, signs and barricades will be installed.
The project involves pipe installation, roadway grading, lime stabilization, asphalt paving and erosion control.
During construction, some inconvenience is to be expected on SW 42nd Street, between W. Hallam Rd. and W. Pella Rd.
Road closings will be posted on the Lancaster County Engineering website prior to the start of construction here.
For more information please see the links below.
Landowner letter - Project communication to residents.
Engineering Plan - A mapped outline of the construction area.
Detour Outline - Proposed traffic detour, from County.